PZU is a creditor of PBG SA (“PBG”) and Hydrobudowa Polska SA (“Hydrobudowa”), both companies with registered offices in Wysogotowo near Poznań, on account of insurance guarantees (contractual guarantees) issued and paid out.
In 2012, bankruptcy proceedings were initiated against PBG and Hydrobudowa. On 21 September 2012, PZU joined the proceedings by notifying its claims to the bankruptcy estate of the two companies.
PBG and Hydrobudowa belong to the same group in which PBG is the parent company. The two companies provided sureties for each other’s liabilities. As a consequence, all claims submitted against the bankruptcy estate of Hydrobudowa in the amount of PLN 101 million were concurrently submitted against the bankruptcy estate of PBG.
On 8 October 2015, the Bankruptcy Court announced a decision in which it approved the composition with PBG’s creditors and on 20 July 2016 it issued a decision to close the bankruptcy proceedings. The decision is final. Following the execution of the composition and reduction of claims to 20.93% of the reported figures, PZU received 206,139 PBG’s bonds with the nominal value of PLN 21 million and 24,241,560 PBG shares with the nominal value of PLN 24 million. The carrying amount of PBG’s shares as at 31 December 2017 was PLN 4 million (zero as at 31 December 2016). Bonds – on 31 December 2017 and an 31 December 2016, they were recognized in off-balance sheet records only and the carrying amount of bonds was zero.
The first list of claims presented by Hydrobudowa’s trustee in bankruptcy to the judge commissioner contained PZU SA’s claims in the amount of PLN 16 million. The final list of claims submitted against the bankruptcy estate of Hydrobudowa has not been determined yet. Bankruptcy proceedings against Hydrobudowa are pending and the determination of the final list of claims is merely an initial step in these proceedings that precedes the drafting of the distribution plan (after the liquidation of the bankruptcy estate).